Do you have a question or concern about this project? Please write us and we will respond to you.

How long will the bridge be closed?

Four weeks. It will take three weeks to build to the superstructure. The bridge will be closed one more week to build and cure the concrete bridge rail, approach rail, and install the bridge membrane and pavement.

How can you be sure the anticipated project schedule will be met?

Contractors are given incentives to complete a job ahead of schedule and financial penalties if they are late. If VTrans were given a grade for on-time delivery of Accelerated Bridge Projects with bridge closures, it would be an A+.

How will the school buses get students to school if the bridge is closed?

The bridge closure will occur during the summer when the school is not in session.

How will the bridge closure affect fire services?

VTrans recognizes that fire service is very important and has developed a plan in collaboration with the Guilford Fire Department and with permission from the Federal Highway Administration to use the emergency access ramp from I-91 just south of the Village of Algiers so that equipment and fire personnel can provide efficient access to the area of town south of the bridge. This ramp will only be open to respond to emergencies and will be closed at all other times.

How will people get mail from the mailboxes located on Grist Mill Road?

VTrans is coordinating with the Brattleboro Post Office to move these mailboxes so that residents south of the bridge can get their mail. The temporary location will be along the I-91 emergency access ramp, located on Route 5 just south of Algiers Village.

Will there be a local bypass detour?

The State detour for this project will be I-91. The Town of Guilford may select a local, non-truck detour route. If a local route in chosen, the Town will be responsible for placing signs on local roads.